Poetic Justice: Obama Library Delayed – Discrimination Lawsuits, Environmental Injunctions, Enrichment Allegations
The Obama Center in Chicago, proposed in 2017 after former President Barack Obama’s presidency, has faced numerous legal challenges and public opposition, delaying its expected opening from 2021 to 2026. Critics argue that the project’s location and deal with the city compromise public trust and could harm the environment by uprooting nearly 1,000 trees and disrupting migratory bird paths. Additionally, the project has incurred significant costs, exceeding $300 million, primarily borne by taxpayers rather than the Obama Foundation.
Support for the center has dwindled, reflected in the foundation’s fundraising decline from over $311 million in 2022 to $129 million in 2023. Recently, a subcontractor filed a $40 million lawsuit claiming racial discrimination against the lead firm, Thornton Tomasetti, which allegedly imposed excessive standards, leading to cost overruns. Thornton Tomasetti defended its actions, stating the subcontractor was “questionably qualified.” Controversy also surrounds compensation for Obama Foundation officials, notably CEO Valeria Jarrett’s annual salary of $740,000. The unfolding issues contribute to a growing skepticism about the project’s viability and implications for the community.
The proposed Obama Center in Chicago has become a towering welter of lawsuits and other issues.
The project was first proposed in 2017 after former President Barack Obama left the White House. From the outset, the project was stalled by resident opposition and other concerns. Once scheduled to open in 2021, the project now as an opening date of 2026.
The Institute for Policy Innovation complained that the center’s “poor location misses valuable opportunities to improve overall land use and economic development in Chicago from putting it elsewhere.”
“The Foundation’s sweetheart deal with Chicago violates the public trust doctrine, and the actual transfer took place without the Foundation meeting either its financial preconditions or the multiple environmental laws protecting key public landmarks. Even at this late date, the deal should be undone.
“If allowed to be completed, the OPC project would uproot close to 1,000 mature trees and disrupt major migratory bird paths that run north-to-south along the shore of Lake Michigan. In total, the public cost of the new roadwork — borne by both the federal government and Illinois, but not the Obama Foundation, of course — probably exceeds $300 million dollars (and growing with inflation), ultimately leaving the already overtaxed and congested system with three fewer north-south lanes than before,” it wrote
As problems have risen, support for the venture has fallen.
In 2023, the Obama Foundation raked in $129.3 million toward its programming and construction, according to the Hyde Park Herald. The year before, it took in $311,359,661.
And now, a Chicago-based subcontractor has filed a $40 million lawsuit, claiming that racial discriminatory practices have harmed the company, according to WFLD.
The suit was filed against Thornton Tomasetti, the lead firm for the $830 million project.
“In a shocking and disheartening turn of events, the African American owner of a local construction company finds himself and his company on the brink of forced closure because of racial discrimination by the structural engineer,” the lawsuit said.
“II in One and its joint venture partners … was subjected to baseless criticisms and defamatory and discriminatory accusations by the Obama Foundation’s structural engineer, Thornton Tomasetti,” the lawsuit said.
The suit claims Thornton Tomasetti altered standards from those of the American Concrete Institute standards, resulting in “excessively rigorous and unnecessary inspection” and major cost overruns.
Thornton Tomasetti has said the subcontractor was “questionably qualified.”
In a memo, the company said it and another firm “bent over backwards to assist what everyone knows was a questionably qualified subcontractor team in areas where more qualified subcontractor would not have required it.”
🚨 The Obama Foundation is facing a $40 million lawsuit over alleged discriminatory building standards at the Obama Presidential Center. 🚨
But this case exposes a bigger problem: how anti-white policies in contracting are destroying businesses. Let’s break it down. 🧵👇 pic.twitter.com/2MwTBGGEMf
— Painter’s Servant (@PaintServant) February 4, 2025
Controversy also surrounds the cost of foundation staff.
Former White House aide and Obama Foundation CEO Valeria Jarrett made $740,000 in one year to run the project, according to the U.K.’s Daily Mail.
Advertise with The Western Journal and reach millions of highly engaged readers, while supporting our work. Advertise Today.
" Conservative News Daily does not always share or support the views and opinions expressed here; they are just those of the writer."
Now loading...